Halfway through the last week of building the sprint to the finish continues – it’s a three-way race between the amazing team from the University of Ljubljana, the rain and the flight home next Tuesday!
The big factor remains the roof which has still not arrived but has been promised for delivery on Thursday evening. If it arrives on time Team University of Ljubljana are favorites to win, but the three days it will take to install means that any delay increases the odds on the flight home winning by a short head, whilst the dark horse is the rain, which is due and could strike at any time.
It’s nail biting stuff, but our money is still on Team University of Ljubljana
Today the roof trusses went up on the kitchen, the concrete was poured for the front veranda and some of the drainage area and more of the doors were hung. Tomorrow work will begin on installing the perimeter fence, which will help to secure the site.
Keep tuned in for more updates!